If soils are below 7 CBR value during site planning, what structural element is planned?

Prepare for the CDC 3E052 Electrical Power Production Journeyman Exam. Utilize flashcards and multiple choice questions complete with hints and explanations. Equip yourself for success!

Multiple Choice

If soils are below 7 CBR value during site planning, what structural element is planned?

Explanation:
Weak soil bearing capacity calls for an anchoring method to transfer loads to deeper, more stable soil. A deadman is a buried anchor connected to the structure by tie-backs, designed to resist uplift and lateral forces. When CBR is below 7, relying on shallow footings isn’t enough, so planners specify a deadman to provide the necessary resistance and prevent movement or tipping under service loads. The other ideas don’t address the load transfer to deeper soils in the same direct way: additional vertical supports help with vertical load but don’t counteract uplift effectively; ground-anchored mats can be used in soft soils but aren’t the specific anchoring solution implied here; a reinforced asphalt patch is a surface remedy, not a load-bearing foundation element.

Weak soil bearing capacity calls for an anchoring method to transfer loads to deeper, more stable soil. A deadman is a buried anchor connected to the structure by tie-backs, designed to resist uplift and lateral forces. When CBR is below 7, relying on shallow footings isn’t enough, so planners specify a deadman to provide the necessary resistance and prevent movement or tipping under service loads. The other ideas don’t address the load transfer to deeper soils in the same direct way: additional vertical supports help with vertical load but don’t counteract uplift effectively; ground-anchored mats can be used in soft soils but aren’t the specific anchoring solution implied here; a reinforced asphalt patch is a surface remedy, not a load-bearing foundation element.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy